Preparation & Planning

What field preparations needs to be done and what planning measures do you need to do?

Before Using the Machine

 

Before Using the Machine for the First Time

  1. Product Inspection
    Upon receiving the machine, a visual inspection should be performed to identify any damage or defects that may have occurred during transport. If any discrepancies are found, the dealer must be notified within three days.
  2. Charging
    The machine has integrated batteries that can be charged by connecting the plug at the front of the generator to a 220V AC outlet with a minimum of 10A. The machine must always be connected to the charger when performing system updates.

    Charging the battery before use reduces the need for power from the generator, thereby decreasing fuel consumption.

Important: Ensure that the machine is connected to a power source before performing a software update

 

Requirements for a Suitable Work Area

  • Must be an agricultural field used for food production.
  • The field must not have a slope greater than 7°.
  • The field condition must not be too wet or muddy.
  • No people or animals should be present on the field.